Uninterrupted PV boom in Spain
The sum of the new systems is ten times the current PV level in the country
. Currently, 5.3 GW are in operation. Most of the approved solar systems are in a waiting position in Andalusia (13.9 GW), Castile-Leon (7.9 GW), Castile-La Mancha (7.1 GW) and Extremadura (6.8 GW). Further projects with a total of 50 GW were still in the approval process of the electricity grid operator at the end of August. There was a rejection for systems with a total of 32 GW.
Wind power is also enjoying unbroken popularity in Spain: at the end of August, projects with a capacity of 23.6 GW had a grid access permit but had not yet been installed. They double the level of all wind turbines installed in Spain.
More articles
Références
Une maison résidentielle à HellenthalGrâce au photovoltaïque, une maison de 50 ans consomme 405 kWh de gaz et 182 kWh d’électricité du réseau par an.
lire la suite...Partenaires
my-PV étend sa compatibilité pour inclure des systèmes provenant d'AtmoceAvec l'intégration du fabricant Atmoce, my-PV étend encore son portefeuille de compatibilité.
lire la suite...L'entreprise
my-PV poursuit sa croissance : Philipp Baumgartner renforce l’expansion internationaleAvec une direction élargie, my-PV se prépare à sa prochaine phase de croissance.
lire la suite...